Here is the latest news on the Camp projects currently underway:

  • We now have a hearing date set for the Conditional Use Permit. At the November 29 hearing, the Hearing Examiner will hear our proposal and listen to any community comments on our application. Both Camp representatives and key leaders in the surrounding community have worked diligently together for several years to prepare a proposal that is acceptable with the community and, we pray, will be approved by the County. Please join in praying for the meeting on November 29. We are still hopeful that our CUP permit will be approved before the end of this year.
  • CL_RR_Construction_250Work is moving ahead on the Cedar Lodge Restroom project. Because of some of the additional projects we have been required to do to bring the building up to current code, the work is taking longer than had been first expected. These projects include installing a sprinkler system on the main level, updating the sprinkler system on the lower level, and adding a fire detection system throughout the building. We also realized that it would save money down the line by re-roofing the center part of the structure as a part of this phase while we were changing the roof-line anyway. These projects have added significantly to the cost of this work and extended the time necessary for completion. We are still hopeful that the new restrooms will be in service by late March or early April, 2012.
  • This time of year is when a lot of our attention turns to preparing for The Lights of Christmas. Work is progressing very well on getting the lights up. We have a great crew this year working on the light-hanging! The other focus right now is on some new mural scenes and sets, and on the displays for the fence surrounding the restroom construction area in front of Cedar Lodge. Beginning the second week of November and continuing through the end of the month, we need a number of volunteers to help midweek with installing the pond scene, Natural Wonders, the nautical scene, preparing numerous panels of artwork and archways, and setting up tents. There are jobs requiring both heavy and light work. November 28-30 is also a key time to finish anything left undone — decorating some remaining facilities that cannot be touched until then, and cleaning up each venue — putting on all of the finishing touches just prior to opening night, December 1. Please pray for safety and a good supply of willing hands to help.
  • Help is still needed on a large firewood cutting and splitting project.

If you would be interested in volunteering to help with any projects, whether you have a few hours or a few days, contact Jessica Wilson at the Camp by phone at 1-800-228-6724 or email jwilson@warmbeach.com.

Add a comment

Here is the latest news on the Camp projects currently underway:

  • amphitheatre325Renovation work on the Amphitheatre is nearly complete, and what a difference it makes! The wooden boards that made up the walkways and seating had deteriorated over the years to the point they gave an unsettling, springy feeling when you walked or sat on them. Thanks to a small army of volunteers, that is a thing of the past. We are still raising the needed funding to cover the rest of the costs of this project (click here to help!). The availability of the volunteer help and the condition of the structure required this project be done as soon as possible, before the funding was all in-hand.
  • The Conditional Use Permit process continues to proceed slowly through the County. We are waiting for yet another round of County planner comments which we will review and respond to. Please pray that the plans will finally be approved this year with few additional revisions required.
  • Renovation work on five staff houses has been completed, receiving different combinations of new windows, new siding and fresh paint. There are several more staff houses waiting for new windows and other improvements in the future. While these projects don’t directly serve our guests, they are important to preserving and maintaining the investments in our staff housing and providing for the care of our staff families.
  • This time of year is when a lot of our attention turns to preparing for The Lights of Christmas. There are a number of new lighting displays that need to be created to cover the restroom construction area in front of Cedar Lodge during The Lights, and painting projects, preparing scenes and sets for the event, to name just a couple.
  • Construction of the new fuel depot area at the shop is nearing completion, and the ten picnic tables have been assembled. Help is still needed on a large firewood cutting and splitting project.

If you would be interested in volunteering to help with any projects, whether you have a few hours or a few days, contact Jessica Beach at the Camp.

Add a comment

Here is the latest news on the Camp projects currently underway:

  • Train_Car_250A new train car for the Polar Express is nearing completion and was actually rolled out during Family Camp week! This special wheelchair-accessible car will enable us to accommodate wheelchair-bound guests on the train. Funding for this project came from a grant from the Tulalip Tribes and the work was accomplished by a team of dedicated volunteers.
  • There are a number of projects going on right now. We have 14 volunteers here for the month of August, and they are really getting a lot of work accomplished. They are rebuilding the Amphitheatre, replacing siding and/or installing new windows in four staff houses. They are also working on painting projects, hosting in the Dining Room, cleaning, sewing, refinishing lobby furniture, and working on decorations for The Lights of Christmas. Wow!
  • We just received the permits from the County for the restroom relocation project in Cedar Lodge. This is a huge praise for which we are very thankful! Construction will begin very soon, and the goal, Lord willing, is to have the new restrooms open in time for The Lights of Christmas in December. Keep praying!
  • The Conditional Use Permit process continues to proceed slowly through the County. Please pray that the plans will finally be approved this year, and with few revisions required.
  • The Warner House is looking great with new exterior paint. The interior of Cascadian Lodge is getting new paint and is about half done so far. Still waiting for volunteers and funding is painting the exterior of Olympic View Lodge, putting together ten picnic tables, constructing a new fuel depot area at the shop, and a large firewood cutting and splitting project.
  • The guest snack area in Cedar Lodge was refurbished by a group of volunteers from the Arlington FM Church.

If you would be interested in volunteering to help with any projects, whether you have a few hours or a few days, contact Jessica Beach 1-800-228-6724, or at jbeach@warmbeach.com.

Add a comment

Here is the latest news on the Camp projects currently underway:

  • The application for permits to do the restroom relocation project in Cedar Lodge has been submitted to the County for approval. This process will take a minimum of three months to complete. Lord willing, the actual work on this first phase of the Cedar Lodge renovation project will begin later this year. After years of talking about moving the restrooms upstairs in Cedar Lodge, it may just be months away from actually happening. Keep praying!
  • The Conditional Use Permit process continues to proceed, albeit slowly, through the County. Please pray that the plans will be approved by the County this year with support from the community and with few revisions required.
  • programcenterA_250At the Program Center, new carpeting for Meeting Room A has been ordered with funding coming from Men’s Advance and Women’s Retreats. Exterior painting is waiting for additional funding, and the railing project in the courtyard is waiting for volunteer labor.
  • Volunteers have taken down the bridge on the Nature Trail in the kettle-hole cirque for safety reasons, and soon we will be dismantling the “McDonald’s” Playland structure for the same reason.
  • Other projects in the works as funding allows include painting the exteriors of Olympic View Lodge and the Warner House, painting the interior of Cascadian Lodge, putting together ten picnic tables, constructing a new fuel depot area at the shop, and cutting, splitting and stacking more than 20 cords of wood.
  • Thanks to the gifts received from a recent letter sent out, we will be installing a new counter top and refinishing the cabinets in the guest snack area of Cedar Lodge and constructing several portable stage sections for our meeting rooms. And, when we have the volunteer labor, we will be installing some park benches.

If you are interested in volunteering to help with any projects, whether you have a few hours or a few days, contact Jessica Beach at 800-228-6724 or jbeach@warmbeach.com.

Add a comment

Here is the latest news on the Camp projects currently underway:

  • The Camp received a review comment letter from Snohomish County a week ago regarding the Conditional Use Permit we’ve submitted. We will be responding with further information and clarifications. So far, the process is proceeding well. Please pray that the plans will be approved this year with support from the community and few revisions required by the County.
  • While we complete the final plans for the Cedar Lodge restroom project and then wait for building permits from the County, work started last month on some major repair work in the dish room that must be done before the main project can be started. This has taken the dish room out of service since early February, requiring the use of disposable tableware to serve our guests. Just a few days ago, we got the dish room back up and running. Now, Lord willing, the actual work on the first phase of the Cedar Lodge renovation project will begin later this year.
  • thumb_Light-TestersWith all of the lights from The Lights of Christmas now back in storage tubs, it is time to start testing each string of lights and making needed repairs. This will take the next seven months to complete. There is a small group of staff and volunteers who are working on this project as they have time, but it is a daunting task to check all 1.2 million lights! Please pray that God will send ample workers to make “light work” of this huge job. Next year when you see all of those lights at the Camp during December, remember the people who made sure they would all light up!
  • W-Bar-B-Cabins250
  • A major refurbishment project is underway in the bunkhouse cabins at W-Bar-B Ranch. New windows have just been installed. Work still to be done includes repainting the interiors, putting down new flooring, and installing new siding. We are also trying to secure funding to install decks on the cabins, as well.
  • Several projects are in the works for this spring. Carpeting in Program Center Meeting Rooms B and C has been installed. The carpeting in Meeting Room A and the exterior painting at the Program Center is waiting for additional funding. The railing project in the courtyard at the Program Center is waiting for volunteer labor. And, plans are in the works to repaint the exterior of one of the Camp’s dorm houses. If you would be interested in volunteering to help with any of these projects, contact Jessica Beach at the Camp at 800-228-6724 or jbeach@warmbeach.com.
Add a comment

240_cedarlodge_drawingHere is the latest news on the Camp projects currently underway:

  • The Camp’s Conditional Use Permit has been submitted to the County. Now it goes through a 120 day evaluation and hearing process. We are hoping that the public hearing where there is opportunity for the community to comment on the plans can take place in February. The County can also require revisions. Please pray that the plans will be approved with support from the community and few revisions by the County.
  • While we complete the final plans for the Cedar Lodge renovation project and wait for building permits, work has begun on some major repair work in the dish room that must be done before the main project can be started. This takes the dish room out of service for about four weeks, requiring the use of disposable tableware to serve our guests. Hopefully, this work will be completed quickly and without any hitches. Lord willing, the actual work on the Cedar Lodge project, first phase — moving the restrooms to the main floor — will begin later this year.
  • The light hanging crew is busy taking down the 1.2 million Christmas lights from The Lights of Christmas. It takes three months to put up all the lights, and about a month to take them down. Then, between February and September when we start the light hanging process all over again, each string must be tested and the broken ones repaired.
  • Projects being prepared for this spring include repainting the interiors and putting down new flooring in the W-Bar-B Bunkhouse cabins, and installing new windows and siding, and painting the exterior of one of the Camp’s dorm houses. At the Program Center, we will be replacing the railings in the Courtyard, putting down new carpeting in two of the meeting rooms, and repainting the exterior walls. If you would be interested in volunteering to help with any of these projects, contact Jessica Beach at the Camp.
Add a comment

Here is the latest news on the Camp projects currently underway:

  • Please continue to pray for the Camp’s Conditional Use Permit. We have a submittal meeting scheduled with the County Planning Department on November 17. Then, the plans go through a 120 day evaluation and hearing process during which time there will be opportunity for community comment on the plans, and the County can require revisions. Please pray that the plans will be approved with support from the community and few revisions by the County. This permit must be approved before we can begin the Cedar Lodge renovation project, and will affect all future development of the Camp for the next 30 years.
  • We continue to work on the final plans for the Cedar Lodge renovation project. Currently, we are finalizing the electrical engineering details and calibrating fire flow and fire suppression in accordance with fire marshal specifications. Our hope is that the final building plans will go to the County in January or February. Lord willing, the actual work on the first phase — moving the restrooms to the main floor — will begin in 2011.
  • Even though funds were raised earlier this year at Men’s Advance and Women’s Retreats to go towards replacing the railings around the Program Center Courtyard and repainting the exterior walls of the Program Center, we have not been able to arrange for the volunteer labor needed to complete the work. We have put this project on hold until next spring.
  • 240_warner_ext03Emergency renovation work has been completed on the Warner House, one of the Camp’s retreat homes. This included re-roofing the house, removing an old fireplace and chimney, and rebuilding a carport. This house is also used during The Lights of Christmas as the Nutcracker Suite, so the work needed to be completed quickly.
  • Projects being prepared for next spring include repainting the interiors and putting down new flooring in the W-Bar-B Bunkhouse cabins, and installing new windows, and siding, and painting the exterior of one of the Camp’s dorm houses. If you would be interested in volunteering to help with either of these projects, contact Jessica Beach at the Camp at 360-652-7575 or 800-228-6724.
Add a comment

Pines LandscapingHere is the latest news on the Camp projects currently underway:

  • The project at the Stables — running a waterline out for a winterized watering trough, and installing a system to collect and pipe away the runoff water from the roofs of all the buildings in the Stables area — has been completed thanks to LZ Construction and the Snohomish Conservation District. This work will help protect the environment in the area around the Stables.
  • We continue to work with building engineers and the architects on the final plans for the Cedar Lodge renovation project. We hope to begin the actual work on the first phase — moving the restrooms to the main floor — in 2011. Actual construction is dependent on getting approval from the State and County agencies involved in the process.
  • Funds were raised at Men’s Advance and Women’s Retreats to replace the railings around the Program Center Courtyard and repaint the exterior walls of the Program Center. We need several volunteers to step forward to help with this work. If we had six or eight men for a day in October, we would be able to complete this project. Otherwise, we will need to hold the work until next spring.
  • Please continue to pray for the Camp’s Conditional Use Permit. We are planning to submit the final application to the County this month. This permit must be approved before we can begin the Cedar Lodge renovation project, and will affect all future development of the Camp for the next 30 years.
  • This is the time of year that we wrap up as many existing projects as possible for the season. We are completing some landscaping around the sidewalks that were put in  last spring near the Pines, and finishing up some maintenance work on a couple of retreat houses.
Add a comment

Here is the latest news on the Camp projects currently underway:

Volunteer-Projects
  • Projects planned for the Stables include running a water line out for a winterized watering trough, and collecting and piping away the runoff water from the roofs of all the buildings to an area away from the manure shed to help protect the environment. This work will be done as manpower is available.
  • We continue to work with building engineers and the architects on the final building plans for the Cedar Lodge renovation project, phases I, II, and III, so that we can submit our plans to the County for building permits. The first phase will be moving the restrooms to the main floor. Actual construction is dependent on receiving our Conditional Use Permit.
  • Funds were raised at Men’s Advance and Women’s Retreats for replacing the railings around the Program Center Courtyard, and repainting the exterior walls of the Program Center. This work will be done when the use of these facilities slows down after the busy summer season, and we have the volunteers available.
  • Work is nearing completion on the installation of the pasture sprinkler system. Once in operation, this system will allow us to irrigate our pastures with treated and reclaimed wastewater, with zero discharge of treated effluent into the bay during the summer seasons.
  • There will be some painting, roofing, and construction projects planned between now and the end of the year on several Camp buildings. If you would like to volunteer to help with any of these, please contact Jessica in our volunteer office.
  • Please continue to pray for the Camp’s Conditional Use Permit application before the County. This permit must be approved before we can begin the Cedar Lodge renovation project, and will affect all future development of the Camp for the next 30 years.

 

Add a comment

Cedar Lodge ArtworkHere is the latest news on the Camp projects currently underway:

  • Full funding has been received for the refrigerator project. The Camp has been mandated by the County Health Department to replace the home-style refrigerators in use in areas where food is served or food concessions are sold, with commercial-grade refrigerators. Between a grant from a foundation, and the gifts from many friends of the Camp, enough funding has come in to purchase all of the new units. Thank you to all who had a part in this!
  • The fence setback project at the Stables is complete. Projects still to be done at the Stables include running a water line out for a winterized watering trough, and collecting and piping away the runoff water from the roofs of all the buildings to an area away from the manure shed to help protect the environment.
  • We are working with building engineers and the architects on final building plans for the Cedar Lodge renovation project, phases I, II, and III, so that we can submit our plans to the County for building permits. The first phase will be moving the restrooms to the main floor.
  • Smaller projects finished or nearing completion include the repair work done on one of the Camp’s waterlines, and renovation work going on in one of the staff homes.
  • There will be several painting, roofing, and construction projects underway this summer on Camp buildings. If you would like to volunteer to help with any of these, please contact Jessica in our volunteer office.

Please continue to pray for the Camp’s Conditional Use Permit application before the County. This permit must be approved before we can begin the Cedar Lodge renovation project, and will affect all future development of the Camp for the next 30 years.

Add a comment

Subscribe to our Blog

Enter your email address:

Delivered by FeedBurner